Today the reasonable weather continued and we soldiered on and completed the first side windows, at the end of the process we acted like a well organised and tolerant team, that is the way most things have improved during the course of the build.
Sooke Nature Watch
West Coast Life
Friday, October 2, 2026
Front Side windows all in.
Wednesday, September 30, 2026
Wednesday : New Additions
We mounted our first large piece of glass this morning, then fitted two more side windows.
The large pane went in very easily, we used a couple of sturdy straps to carry it over from the work area and initially clamped it into place while installing a few of the strips that will run all around the perimeter, once it was installed and safe, we moved on and removed the temporary column and constructed the frame for the two other single pane windows.
Monday, September 28, 2026
First Two Windows
The roof was finished yesterday, it was an odd day, even though we organized ourselves a lot better, the time still drifted away and another five hours slipped through our fingers, however, it was done and we are very happy with the results.
Today, as promised, we fitted our first two windows.
We noticed that six of the eight windows were 33" tall and not 34" so we changed our plan slightly, it meant that both of those 34" windows had not been pre-painted grey, so this one will need to be painted in place which will be a bit more fiddly, but it will get done.
We will do it, but not today!
It means that as each day passes, as we add windows, the greenhouse should become more waterproof, we have rain forecast for the next 24 hours, so we are not sure if any progress will be made in the morning.
Saturday, September 26, 2026
Now we're talking....
Saturday. Four and a half hours. Half done, the rest of the roof will be finished tomorrow.
Thursday, September 24, 2026
Rain stopped play.
The first front hole, designated F1 has now been filled.
Wednesday, September 23, 2026
Preparing to fill in the holes
The fascia boards have been installed and we are left with the 12 holes on the roof to fill in.
At the top right of the picture you can see the first "test" cross beam with "bottom" H-channel attached that has been fitted to retain the upper piece of polycarbonate and also to work out the smaller piece dimensions. If you can visulaize the area, the required piece should be 24" wide and about 11" long which, due to all our tolerances and lack of straightness, will vary for each bay.
Once the two fascia boards were fitted (which also have bottom H-channel attached to the top surface) the dimensions of each piece front F1-F6 and back B1-B6 will be worked out one by one, when all twelve pieces are cut and in place, two long pieces of "top" H-channel will be clipped in down the sides and all will be retained. It should be noted that also every bay, F1-F6 and B1-B6 will have a short 22" piece of top H-channel to clip on which splices the two pieces of polycarbonate sheet.
Up to speed?
All pieces of top and bottom H-channel will be clipped into place and the roof should be complete and we know what will be next after that :
Considering that all the other holes need to be filled and painted, the front side windows are being prepainted before being installed. They are being painted grey and the retaining surrounds will be brown, as someone pointed out, we are not painting the windows as that would be silly.
The daily quota for painting is definitely around the three mark. Any more than that is just out of the question.
Monday, September 21, 2026
Major Milestone Days
Yesterday and today we danced with the big ladder and installed the majority of the twin walled polycarbonate sheets, each measuring 24" x 48" and approximately 0.25" thick. The sheets had been taped at the top and after a learning curve day on Sunday, today we completed the optimized "production line" of positioning each sheet, placing the upper H-channel in position, applying the correct caulk and adhesive at the top, installing a shingle on top of that then installing the EZ-Ridge XT on top, all while dancing with that ladder, making sure we were safe, dropping things, losing things, forgetting things...

