The "centre" post has been added with the two 4x4 pieces for the lower window frames, I use quotes there because all our tolerances have stacked up and if we measure the centre at top and bottom, the post does not look true to the greenhouse frame, and the visual is everything.
Sooke Nature Watch
West Coast Life
Tuesday, October 6, 2026
New Post, like the old one
Monday, October 5, 2026
The Final Wall - planning stage
The last two patio windows were installed today, so that leaves a hole to put a door in and the final wall windows, as with the first wall of windows, planning is required :
Sunday, October 4, 2026
Painted and then around the bend.
We painted the frames yesterday and removed the masking tape this morning, then we installed the middle window that we had obtained from a local chap called Sunny on marketplace, it was a heavy window but we wrangled it into our frame quite easily and screwed it in, there will be some trim work to be done on the outside and inside.
In addition another large sheet of 34" x 76" patio door glass was moved over from the work area using our strap system and safely installed even though we are running out of places to use clamps.
The layout of the windows for the back wall has been mapped out and it looks like we will have enough wood in stock to complete the greenhouse. It may be desired to buy a couple of correct sized pieces for various trim work, however, we will attempt to resist as we know money can always be better used by buying beers.
Friday, October 2, 2026
Front Side windows all in.
Today the reasonable weather continued and we soldiered on and completed the first side windows, at the end of the process we acted like a well organised and tolerant team, that is the way most things have improved during the course of the build.
Wednesday, September 30, 2026
Wednesday : New Additions
We mounted our first large piece of glass this morning, then fitted two more side windows.
The large pane went in very easily, we used a couple of sturdy straps to carry it over from the work area and initially clamped it into place while installing a few of the strips that will run all around the perimeter, once it was installed and safe, we moved on and removed the temporary column and constructed the frame for the two other single pane windows.
Monday, September 28, 2026
First Two Windows
The roof was finished yesterday, it was an odd day, even though we organized ourselves a lot better, the time still drifted away and another five hours slipped through our fingers, however, it was done and we are very happy with the results.
Today, as promised, we fitted our first two windows.
We noticed that six of the eight windows were 33" tall and not 34" so we changed our plan slightly, it meant that both of those 34" windows had not been pre-painted grey, so this one will need to be painted in place which will be a bit more fiddly, but it will get done.
We will do it, but not today!
It means that as each day passes, as we add windows, the greenhouse should become more waterproof, we have rain forecast for the next 24 hours, so we are not sure if any progress will be made in the morning.
Saturday, September 26, 2026
Now we're talking....
Saturday. Four and a half hours. Half done, the rest of the roof will be finished tomorrow.

